# Workload and capacity
|
||
|
||
## What it is
|
||
|
||
Member menu → **Workload and capacity** (`/workload`) shows, week by week, how
|
||
much work each person has against the hours they have, across every board you
|
||
work on. It answers the questions a board's Swimlanes per member and the
|
||
board's own *Workload* chart (a count of open cards per person) cannot: who has
|
||
too much in a given week, who could take more, and what a coming project needs
|
||
before anybody is named.
|
||
|
||
## Read more
|
||
|
||
- [Resource management](https://en.wikipedia.org/wiki/Resource_management)
|
||
and [Capacity planning](https://en.wikipedia.org/wiki/Capacity_planning) on
|
||
Wikipedia - planning work against the people's available time.
|
||
- [Utilization rate](https://en.wikipedia.org/wiki/Utilization_rate) - the
|
||
billable utilization shown under each name.
|
||
- [Professional services automation](https://en.wikipedia.org/wiki/Professional_services_automation)
|
||
- the kind of tool this and [Budget and billing](../Billing/Billing.md) are
|
||
part of.
|
||
- [Story point](https://en.wikipedia.org/wiki/Story_point) - the unit of the
|
||
Scrum estimates it can sum.
|
||
- In WeKan: [Budget and billing](../Billing/Billing.md),
|
||
[Pages](../Pages/README.md).
|
||
|
||
## How to use it
|
||
|
||
1. Open the member menu (your avatar in the header bar) and choose **Workload
|
||
and capacity**. It is there while Admin Panel / Settings / Features keeps
|
||
the feature on.
|
||
2. Choose **From** (the first week), **Weeks** (4, 8, 12 or 26) and **Show**
|
||
(hours or story points); an administrator may choose **All boards**.
|
||
3. Read each person's row week by week; click a week to see its cards.
|
||
4. Under **My working time**, set **Hours per week**, **Work time percent**,
|
||
**Working days**, **Billable target** and **My skills**, and click **Save**.
|
||
5. Under **My absences**, click **Add absence**, choose the type, the start and
|
||
the end, and save.
|
||
6. A board admin adds **Allocations** (**Add allocation**): a person, or a role
|
||
with a headcount for a placeholder, a percent and a period. An administrator
|
||
adds **Public holidays** (**Add public holiday**).
|
||
|
||
### What is counted
|
||
|
||
- **Hours.** Each card can have **Estimated hours**, set in the card's *Time*
|
||
section beside the time spent (the same popup). What is still to do is the
|
||
estimate less the time spent, never below zero. A board whose Scrum estimate
|
||
unit is hours (`h`, `hours`, `tunti`, ...) counts its Scrum estimates as hours
|
||
for cards that have no estimate of their own.
|
||
- **Story points.** On a board with Scrum on, the board's estimate (Planning
|
||
Poker or the numeric custom field chosen in Scrum settings) is summed as
|
||
points. *Show* switches the table between hours and points.
|
||
- **Who carries a card.** Its assignees, shared equally; a card with no
|
||
assignee is carried by its members. A card nobody carries is shown once, on
|
||
the *Not assigned to anybody* row.
|
||
- **When.** A card's work is spread from its start (or received) date to its
|
||
due (or end) date, over the days the person works, in proportion to their
|
||
hours on each day. Work whose dates are past is due now and is counted
|
||
today, and the card is counted as overdue. A card with no dates is shown
|
||
under *No dates*; a card with no estimate is counted under *Cards without an
|
||
estimate*. Finished (due complete) and archived cards count nothing.
|
||
|
||
### Capacity
|
||
|
||
- **My working time**: hours per week (default 37.5), work time percent (a
|
||
part-time 60 % of 37.5 h is 22.5 h) and the working days. A day's hours are
|
||
the week's hours shared over the working days.
|
||
- **My absences**: vacation, sick leave, day off, training or other, from one
|
||
day to another. An absent day has no hours, and work spread over a period is
|
||
moved to the days the person is there.
|
||
- **Public holidays**: set by an administrator on the same page; a day off for
|
||
everybody.
|
||
|
||
A week is **red** when its work is more than its hours (over 100 %), when the
|
||
person's allocations add up to more than 100 %, or when there is work and no
|
||
hours at all (an absence). It is **grey-blue** when it is under half full. Click
|
||
a week to see the cards in it.
|
||
|
||
### Utilization
|
||
|
||
Under each person's name, the report shows their **billable utilization**:
|
||
the hours they logged on billable cards in the report's weeks, against the
|
||
hours they had. **Billable target** in *My working time* sets the share they
|
||
aim for; under it, the figure is red. Time logged on a card marked not
|
||
billable counts as logged, not as billable. Only the time on the boards of the
|
||
report is counted.
|
||
|
||
### Skills
|
||
|
||
*My working time* also lists a person's **skills**, each with a level 1 to 5
|
||
("React 4, Go, Finnish 5"; 3 when not given). A placeholder can name the
|
||
**skill it needs** and the lowest level that will do; its row then shows who
|
||
**could do it** - the people of the report with that skill at that level or
|
||
better, the most free hours first over the weeks it needs them. Free hours
|
||
are the hours a person has less the work they carry or the time promised to
|
||
boards, whichever is more.
|
||
|
||
### Allocations and placeholders
|
||
|
||
A board's admins can allocate a share of a person's time to the board for a
|
||
period - "A works on board X 50 % of their time in April" - shown in each week
|
||
as a percent beside the load. Without a person, an allocation is a
|
||
**placeholder** for a role: "Developer × 1, 100 %, next month" is drawn as its
|
||
own row with the hours it will need, so a project can be planned before the
|
||
people are chosen. A person allocated must be an active member of that board.
|
||
|
||
## How the numbers are calculated
|
||
|
||
All in [models/lib/workload.js](../../../models/lib/workload.js):
|
||
|
||
- **Hours a person has on a day** = hours per week × work percent / 100 /
|
||
number of working days, and 0 on a day that is not a working day, a public
|
||
holiday or an absence (`dayCapacity`). Defaults: 37.5 hours, 100 %, Monday to
|
||
Friday.
|
||
- **Hours still to do on a card** = estimated hours - time spent, never below 0
|
||
(`remainingHours`). A card's hours and points are divided equally between the
|
||
people who carry it.
|
||
- **Spreading**: the days from the start (or received) date to the due (or end)
|
||
date; each day gets the person's hours that day divided by the sum of their
|
||
hours over those days. With no working day in the span, everything falls on
|
||
its last day. A span already past is moved to today and counted as overdue;
|
||
a span that has started counts from today. At most 3 × 366 days are spread.
|
||
- **Utilization** of a week = load hours / capacity hours × 100, rounded; null
|
||
when there is load and no capacity. **Billable** = billable hours logged /
|
||
capacity hours × 100, rounded.
|
||
- **Red (over)**: load hours > capacity hours, or allocations > 100 %, or load
|
||
with no capacity. **Grey-blue (under)**: not over, with capacity, load under
|
||
50 % of capacity and allocations under 50 %.
|
||
- **Allocations** add `percent` of the week's covered hours to the person (or,
|
||
for a placeholder, `percent` × headcount as the hours it will need). A
|
||
percent is 1-100, a headcount 1-100, a skill level 1-5 (3 when not given; a
|
||
placeholder's lowest level 1 when not given), at most 30 skills a person.
|
||
- **Report limits**: 1-26 weeks (`MAX_WEEKS`); at most 500 boards, 500 people,
|
||
20,000 cards and 100,000 time entries ([server/workload.js](../../../server/workload.js));
|
||
beyond that the page says *Too much to show at once*. Hours are rounded to
|
||
two decimals.
|
||
|
||
## How it works in WeKan
|
||
|
||
### Who sees what
|
||
|
||
- A report covers the boards you are an active member of, except boards where
|
||
you only see the cards assigned to you, and the active members of those
|
||
boards. Public boards are not included: somebody's workload is not public
|
||
because one of their boards is. An administrator may choose *All boards*.
|
||
- Only the cards of those boards are counted, and the cards themselves never
|
||
reach the browser: the server computes the report and sends the numbers.
|
||
- Somebody else's absence is shown only as days absent. Its type and note -
|
||
whether somebody is sick, and why - are shown only to that person and to
|
||
administrators.
|
||
- Your working time and absences are yours to change; an administrator can
|
||
change anybody's. Allocations are changed by the board's admins, holidays by
|
||
administrators.
|
||
|
||
### Code
|
||
|
||
| | |
|
||
| --- | --- |
|
||
| `models/lib/workload.js` | the rules, as pure functions: capacity, spreading, allocations, placeholders |
|
||
| `models/lib/workloadView.js` | how a week is drawn: colour, bar, text |
|
||
| `models/workload.js` | the collections `workloadCapacities`, `workloadAbsences`, `workloadHolidays`, `workloadAllocations` - no client writes, no publications |
|
||
| `server/workload.js` | the methods, with who may call them |
|
||
| `client/components/main/workload.*` | the page |
|
||
| `tests/workload.test.cjs` | the rules; `tests/workloadAccess.test.cjs` who may do what |
|
||
|
||
The browser tests are
|
||
[tests/playwright/specs/workload-capacity.e2e.js](../../../tests/playwright/specs/workload-capacity.e2e.js).
|
||
|
||
## Commits
|
||
|
||
- [Saves show, forms render and PDFs print in Workload, Budget and billing](https://github.com/wekan/wekan/commit/1032b472f3264e82c1cb860e59ebda3719f374ef)
|
||
- [Utilization, billable target and skills](https://github.com/wekan/wekan/commit/d88662d69c212650a7ed5d0ab82d69262a2c6690)
|
||
- [Workload and capacity: hours against working time, across boards, with absences and allocations](https://github.com/wekan/wekan/commit/165dfa3c1676f6069d456ead021fa0db69f92e22)
|