Lauri Ojansivu b0803ffeaa Import Jira sprints, fix versions, rank and epic links as Scrum planning data.
The Sprint, Rank and Epic Link fields are found by their schema type, or
by name when the export has no schema, never by customfield number.
Future and active sprints become planned WeKan sprints with their goals
and dates. An active sprint is reported, because the export has no
commitment snapshot. Closed sprints are reported, not invented. Fix
versions become releases. Jira's rank orders the backlog, and a legacy
Epic Link becomes the card's parent. The data is written as a native
Scrum import, and these fields are no longer also imported as text
custom fields.

Thanks to xet7 !
2026-10-02 19:21:24 +03:00
..

Right sidebar

Open the sidebar on a board. Its main view provides Board Settings, members, labels, a vertical-scrollbar preference and activities. Keyboard shortcuts and accessibility controls are available from the sidebar controls.

Show week of year (ISO 8601) is now in Board Settings / Date, below Save and a horizontal rule. It changes your week-number display preference.